EU PREPROD - TP 8.0.5 Rollout from 2025-04-23 08:00 UTC to 2025-04-23 15:00 UTC

Scheduled maintenance Test and pre-production platform EU PREPROD API and GUI Network Server for ThingPark Wireless and Enterprise Thingpark FUOTA Join Server for ThingPark Activation
2025-04-23 08:00 UTC · 7 hours

Updates

Monitoring

Upgrade is completed

April 23, 2025 · 13:30 UTC
Update

Upgrade is started.

April 23, 2025 · 08:00 UTC
Update

Upgrade is started

April 23, 2025 · 08:00 UTC
Scheduled

Actility Network Operations is going to install Thingpark Wireless and Enterprise 8.0.5 on EU PREPROD platform.

Please find details in release notes:
📝8.0 Maintenance Release Notes (for customers)
📝8.0 ThingPark Enterprise SaaS ChangeLog

This is a minor release with the following impacts

  • Packets may be lost or queued during network server switchover
  • UI will be closed during part of the maintenance
April 17, 2025 · 07:59 UTC