AU PREPROD TP 7.3.6a rollout from 2024-09-11 08:00 UTC to 2024-09-11 14:00 UTC

Scheduled maintenance Test and pre-production platform AU PREPROD Network Server for ThingPark Wireless API and GUI ThingPark X IoT-Flow
2024-09-11 08:00 UTC · 6 hours

Updates

Resolved

Upgrade is completed.

September 11, 2024 · 14:00 UTC
Update

Upgrade is started.

September 11, 2024 · 08:14 UTC
Scheduled

Actility Network Operations is going to install ThingPark Wireless and Enterprise 7.3.6a on AU PREPROD platform.

Please find details in the release notes:

This is a major release with the following impacts

  • Packets may be lost or queued during network server switchover
  • User may have to re-enter login information in GUI or API
  • The provisioning (all API and UIs) will be closed during part of the maintenance window
September 5, 2024 · 14:02 UTC